Salus were pleased to be appointed by existing client, Mirus Management Services, to provide Approved Inspector services for this 14,500 m² warehouse building with two storey office accommodation.

Salus performed 18 site inspections over an eight month contract period, including the witnessing of an air test.

The project was managed by Adrian Sawyer of Salus’ Corby office, while the site inspections were performed by two surveyors from the Dursley, Gloucestershire, office, thus reducing costs and time.

Client: Innovate Logistics

Architect: Peart Bradley Architects

Project Managers: Mirus Management Services

Contract Period: 8 Months

Construction Cost: Multi-Million